PV PIPE cung cấp hơn 1363 tấn ống thép kết cấu API 2B cho Dự án SHWE (Giai đoạn 3)
Project SHWE phase 3 is located in the Bay of Bengal, off the coast of Rakhine state, Myanmar with the aim of constructing and installing technology platforms for drilling wells at gas fields in Shwe and Shwe Phyu. PTSC M&C of Vietnam plays a role as the contractor for the construction of the foundation for this project. PV PIPE is the unit supplying 1363 tons of structured steel pipes for the foundation part.
Product: Structural steel pipe
Time: From November 2021 to March 2022
Technical specifications
Product Specification: API 2B
Steel Grade: API 2W Gr50/ API 2W Gr50Z
Outer Diameter (mm): 750 – 1350 mm
Wall Thickness (mm): 15-25 mm
Total Length (Km): 2.6
Quantity (tons): 1363